The project manager is reorganizing a team to develop a new product.The company’s technology experts reviewed the standard,and expresses concern that the quality of the product can only be test the new product’s new function in system testing phase.This could cause polential schedule and budget delays.What should the project manager do upon learning this information?
A.
Review project management plan to reflect delays to the schedule and budget.
B.
Inform stakeholders and definite this polential delay.
C.
Update project schedule to account for possible delays.
D.
Update the risk register,which contain the acceptance testing and mitigation plan.