【单选题】● During the planning phase of a project, you realize that more than one functional department possesses the skill and technical know-how to perform. a given task. The best way for the project manager...
A.
Make the decision, document it in the linear responsibility chart, and distribute the chart to all departments.
B.
Let the affected line groups decide among themselves who will perform. the work
C.
Ask the executive sponsor to make the decision
D.
Allow each line group to perform. part of the task
【单选题】During planning you sit down and estimate the time needed for each task and total them to come up with the project estimate This duration is what you commit to complete the project. What is wrong with...
A.
The team did not create the estimate and estimating tales too long using that method
B.
The team did not create the estimate and a network diagram was not used
C.
The estimate is too long and should be created by management
D.
The project estimate should be the same as the customer's required completion date