【单选题】During a meeting with some of the project stakeholders, the project manager is asked to add work to the project scope of work . The project manager had access to correspondence about the project befor...
A.
let the sponsors know of the stakeholders' request .
B.
evaluate the impact of adding the scope of work .
C.
tell the stakeholders the scope cannot be added .
D.
add the work if there is time available in the project schedule .
【单选题】93 When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget.
A.
Reduce features and/or functionality
B.
Increase risk.
C.
Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)