The first phase of a project is the feasibility study. According to the PMBOK, which of the project management process group does the feasibility study phase need
A.
Plannin
B.
Planning and monitoring & controllin
C.
Initiating and closin
D.
All of five process groups: initiating, planning, executing, monitoring & controlling, and closin