61 Cost and schedule data are usually integrated because:
A.
optimized project cash flow can affect financial requirements
B.
they provide MIS with an integrated system to produce reports
C.
they control escalation allowances
D.
they account for omissions in the definitive estimate
E.
they predict future performance