【单选题】129 The major difference between PERT and CPM networks is:
A.
PERT requires three time estimates whereas CPM requires one time estimate.
B.
PERT is used for construction projects whereas CPM is used for R & D.
C.
PERT addresses only time whereas CPM also includes cost and resource availability.
D.
PERT requires computer solutions whereas CPM is a manual technique.
E.
PERT is measured in days whereas CPM uses weeks or months
【单选题】身份认证的目的包括:保证交易者是交易者本人、避免与超过权限的交易者进行交易和_______。
【单选题】In PERT, a basic issue is the minimization of total:
B.
Cost of all activities
【判断题】西奥多·舒尔茨是著名的研究人力资本的学者,他1959年提出的《人力资本:一个经济学的观点》以及1960年提出的《人力资本投资》标志着人力资本理论的繁荣。
【单选题】The major difference between PERT and CPM networks is:
A.
PERT requires three time estimates whereas CPM requires one time estimate.
B.
PERT is used for construction projects whereas CPM is used for R & D.
C.
PERT addresses only time whereas CPM also includes cost and resource availability.
D.
PERT requires computer solutions whereas CPM is a manual technique.
E.
PERT is measured in days whereas CPM uses weeks or months.