【单选题】某项工作A分别有两项紧前工作甲、乙和一项紧后工作丙。已知甲工作的最早开始时间为2,持续时间为3;乙工作的最早开始时间为3,持续时间为3;丙工作的最早开始时间为10。当工作A的持续时间为2时,其自由时差为( )。