When the initial cost of a project exceeds the present value of the cash inflows, then the project should be:
A.
accepted because the internal rate of return is positive.
B.
accepted because the profitability index is greater than 1.
C.
rejected because the profitability index is less than 1.
D.
rejected because the internal rate of return is negative.