【单选题】In the process of implementing the project,you discover a deliverable has not received.The seller it is not the content of the contract,but you remember clearly before you discussed this matter,even r...
A.
The deliverables may be described in the specification requirements,and not in the contract.
B.
Required to complete the deliverable.
C.
Submit requests for contract changes,in order to obtain the deliverables.
【单选题】Which of the following is not an indicator that revenue can be recognized over time?
A.
The seller is enhancing an asset that the buyer controls as the service is performed.
B.
The customer consumes the benefit of the seller's work as the seller performs the service.
C.
The seller is creating an asset that has an alternative use to the seller, and the seller can receive payment for its progress even if the customer cancels the contract.