【单选题】● The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, t...
A.
measure, delay, record, distribute, analyze, and direct
B.
plan, schedule, monitor, control, report, and forecast
C.
promote, highlight, monitor, control, forecast, and report
D.
emphasize, visualize, analyze, conceptualize, report, and record