11 When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget. A. Reduce features and/or functionality B Increase risk. C. Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times) D. All of the above. E.