【简答题】P Co has the following contract in progress ($'000) Total contract price500 Costs incurred to date220 Estimated costs to completion330 Payments invoiced and received210(1)What's the pencentage o...
【单选题】Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the: